All tools

Oil & Gas · Professional Microtool

Separator Sizing Calculator

Diameter · Height · Vapour velocity

Size a vertical two-phase separator: Souders-Brown for the diameter the gas needs to disengage, retention time for the height the liquid needs to settle, and the next fabricated size up.

9 inputs Screening estimate for preliminary vessel sizing No registration Nothing you enter leaves your browser

Feed Gas out Liquid out Height Vapour velocity Maximum allowed

Start from an example: 25 MMSCFD with 300 m³/day of condensate at 60 bar a →

Feed

Vapour rate at standard conditions. The vessel sees the much smaller actual volume at operating pressure.

Total liquid rate to be held for retention. This sets the height, not the diameter.

Operating conditions

Absolute pressure in the vessel. Higher pressure means denser gas, less actual volume and a markedly smaller diameter.

Temperature in the separator, which sets gas density along with the pressure.

Fluid properties

About 19 for associated gas. Heavier gas is denser, which helps the separation.

Average Z at the operating condition.

820 kg/m³ for a light condensate, close to 1,000 for water. Only the difference from the gas density matters.

Sizing basis
m/s

Souders-Brown K for the internals fitted. 0.107 m/s (0.35 ft/s) is the common base for a mesh pad at low pressure, but K falls as pressure rises — the suggested value below tracks that. Without a mist extractor, use roughly half.

How long the liquid must stay in the vessel. Two to five minutes is typical; foaming or viscous crude needs far longer.

Full output

  • Minimum diameter
  • Vessel height
  • Height to diameter
  • Maximum vapour velocity
  • Suggested K at this pressure
  • Actual vapour velocity
  • Margin below the limit
  • Liquid height
  • Retention volume
  • Gas density
  • Actual gas volume

Minimum vessel diameter against operating pressure

Diameter falls with roughly the fourth root of pressure, because denser gas means both less actual volume and a higher allowable velocity. Separating early, at pressure, buys a far smaller vessel than separating after a let-down.

Keep it

Both carry the figures you entered, in the part of the address that is never sent to a server. Share only where that is appropriate. To keep a copy for a project file, print the page — it lays itself out as a document.

Need sizing against a real feed characterisation?

We can work from your actual fluid data, slug and surge behaviour and internals selection, and build it into your facility engineering workflow.

Discuss your use case →

Calculation basis 6 steps · view the method →
  1. Gas density = P·MW ÷ (Z·R·T)
  2. Actual gas volume = mass flow ÷ gas density
  3. Maximum velocity = K × √((ρ liquid − ρ gas) ÷ ρ gas)
  4. Minimum diameter from the area that velocity requires
  5. Liquid height = liquid flow × retention time ÷ vessel area
  6. Height = liquid height + inlet zone, disengagement space and mist extractor
Assumptions & limitations Screening estimate for preliminary vessel sizing · 7 assumptions →

This is a preliminary sizing aid, not a vessel design. It covers a vertical two-phase separator in steady service and excludes slug and surge behaviour, foaming and emulsions, three-phase water separation, inlet device selection, nozzle sizing and momentum limits, level instrument spans, and all mechanical design — thickness, code, materials and relief. Mechanical design must follow the applicable pressure vessel code with a qualified engineer, and the process duty should be confirmed against a real feed characterisation.

  • Vertical two-phase vessel with a mesh mist extractor, in steady service.
  • Souders-Brown with the K factor entered. K is not a constant: the suggested value follows the usual screening correlation, which walks K down from 0.35 ft/s as pressure rises above 100 psig. It takes no account of foaming, surface tension or the specific internals.
  • Slug and surge volume is not included — a slug catcher or surge allowance is a separate calculation.
  • The height allowance above the liquid is a screening stack: 0.6 m inlet zone, disengagement of at least 0.9 m or half the diameter, and 0.3 m for the mist extractor.
  • Diameters are rounded up to 6-inch increments; fabricators may offer a different set.
  • Three-phase separation, water dropout and emulsion behaviour are out of scope.
  • Nothing mechanical is calculated: thickness, nozzles, supports, relief and code compliance are all separate work.

Worked examples

About this tool

A separator has two independent jobs and they set two different dimensions. The gas has to slow down enough for droplets to fall out, which fixes the diameter; the liquid has to sit still long enough to degas, which fixes the height. This tool keeps them apart so each assumption — the K factor, the retention time — can be argued on its own. Written for process and facilities engineers doing preliminary work.

Go deeper

Natural Gas Pipeline Pressure Drop calculator

Where the separated gas goes next, and what the line costs it.

Open →

Oil & Gas Operations challenge

Separation, custody transfer, allocation and volume correction.

Open →

Digital Twins & Asset Management challenge

Keeping the model of a facility honest about the plant it describes.

Open →

Talk to the engineers behind it →