Transformer Loading calculator
What the size you chose costs in losses, efficiency and top-oil temperature.
Power & Utilities · Interactive Engineering Model
Demand · Requirement · Standard rating
Change the connected load and the judgements around it — demand factor, power factor, growth allowance, target loading — and watch the requirement move continuously while the transformer you can order jumps to the next standard size.
Sum of the nameplate loads to be supplied, before the demand factor is applied.
Maximum coincident demand as a share of connected load — at or below 100%. This is the demand factor; diversity factor is its near-inverse (the sum of individual maxima over the coincident maximum) and is greater than one, so the two must not be swapped.
Expected power factor of the demand, after any correction you intend to install.
How heavily you intend to load the unit at the design condition. 80% is common; higher accepts less margin for growth and heat.
Start from an example: 1,200 kW connected, 70% demand factor, 25% growth, loaded to 80% →
Move a parameter and the substation answers: the demand the site actually makes, the capacity that demand asks for, and the size anyone would actually install.
The link carries the figures you entered, in the part of the address that is never sent to a server.
Change one assumption at a time. The model updates from the same calculation used for the reported result.
Increase connected load slowly. Watch the calculated requirement move continuously — and the selected transformer jump discretely to the next standard size.
We can work from real load profiles, forecast growth, motor starting and redundancy — and put the result into your planning workflow rather than a spreadsheet.
Demand = connected load × demand factor—Apparent power = demand ÷ power factor—With growth = apparent power × (1 + growth allowance)—Requirement = demand with growth ÷ target loading—Standard rating = the next size available at or above the requirement—This is a preliminary selection aid, not a design. It does not consider motor starting or inrush, short-circuit contribution and downstream fault levels, harmonic derating for non-linear load, altitude and ambient derating, redundancy or N-1 arrangements, or the loss evaluation that often decides between two candidate ratings. Confirm against the applicable standard and the manufacturer's data.
Sizing is a chain of judgements and then a rounding. Demand factor, power factor, growth allowance and target loading each scale the requirement; the answer is then taken up to a size that is actually manufactured. The step between the two is capacity you own and pay for in core loss every hour it is energised. The model shows the chain and the rounding separately, because they are argued about separately.
What the size you chose costs in losses, efficiency and top-oil temperature.
Transformers, substations, feeders and protection coordination.
A pilot-ready enterprise platform for the electric-utility industry.